SUMMARY

The following formula will calculate how many weekdays fall between two weekdays, where startdate and enddate are the two dates:

   =enddate-startdate-INT((enddate-startdate)/7)*2-
   IF(WEEKDAY(enddate)<WEEKDAY(startdate),2)

The starting and ending dates must be actual weekdays. If either of them fall on a weekend, this calculation will not be accurate.


KBCategory: kbother
KBSubcategory:

Additional reference words: noupd


THE INFORMATION PROVIDED IN THE MICROSOFT KNOWLEDGE BASE IS PROVIDED "AS IS" WITHOUT WARRANTY OF ANY KIND. MICROSOFT DISCLAIMS ALL WARRANTIES, EITHER EXPRESS OR IMPLIED, INCLUDING THE WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE. IN NO EVENT SHALL MICROSOFT CORPORATION OR ITS SUPPLIERS BE LIABLE FOR ANY DAMAGES WHATSOEVER INCLUDING DIRECT, INDIRECT, INCIDENTAL, CONSEQUENTIAL, LOSS OF BUSINESS PROFITS OR SPECIAL DAMAGES, EVEN IF MICROSOFT CORPORATION OR ITS SUPPLIERS HAVE BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES. SOME STATES DO NOT ALLOW THE EXCLUSION OR LIMITATION OF LIABILITY FOR CONSEQUENTIAL OR INCIDENTAL DAMAGES SO THE FOREGOING LIMITATION MAY NOT APPLY.

Last reviewed: November 2, 1994
© 1998 Microsoft Corporation. All rights reserved. Terms of Use.