Scheduler Overwrites Package Property InformationLast reviewed: April 22, 1997Article ID: Q122382 |
The information in this article applies to:
SYMPTOMSAfter Scheduler processes a job on a package, the package information is written back into the original database overwriting any changes that were made to the package properties by the Administrator. For example, when the Scheduler reads and compresses a package, it may take a long period of time, depending on the size of the package. During the same time, the Administrator may be changing the properties of the package. This information is overwritten when Scheduler completes the process.
STATUSMicrosoft has confirmed this to be a problem in Systems Management Server version 1.1. This problem has been corrected in Systems Management Server version 1.2.
|
Additional query words: sms prodsms