PCMSVC32 Reports Incorrect Job Status for Completed JobsLast reviewed: April 24, 1997Article ID: Q149672 |
The information in this article applies to:
SYMPTOMSThe Package Command Manager (PCMSVC32) for Windows NT may report an invalid job status when a job has been completed. Instead of being designated "complete," the job status is given as "retrying." The following information is taken from the Pacman.log file: >>> The process handle is #20 >>> Execution error #20 detected. >>> Flagging this process as bad with handle #-1 Ending LaunchScript.................. Package executed. Monitoring the job. Job completed. Reporting job status. Beginning ReportOnProcess...........>>> An error was detected while attempting to run the job.
CAUSEThis problem occurs when a process handle is less than 32.
STATUSMicrosoft has confirmed this to be a problem in Systems Management Server version 1.1. This problem has been corrected in Systems Management Server version 1.2.
|
Additional query words: prodsms
© 1998 Microsoft Corporation. All rights reserved. Terms of Use. |