Scheduler Start of a Job Takes One Second Per ComputerLast reviewed: April 24, 1997Article ID: Q154861 |
The information in this article applies to:
SYMPTOMSIf a job is sent to a large number of computers (for example: 50,000 computers) in a site, the starting of the job by the scheduler can take up to 14 hours, regardless of when the job is to start.
CAUSEScheduler is single-threaded and adds computers one at a time, which takes about 1 second per computer.
STATUSMicrosoft has confirmed this to be a problem in Systems Management Server version 1.1. This problem has been corrected in Systems Management Server version 1.2.
|
Additional query words: prodsms
© 1998 Microsoft Corporation. All rights reserved. Terms of Use. |