Platform SDK: Exchange Server

CompletedDate

The CompletedDate property specifies the date when a task was completed.

Applies To

Task object

Data Type

Date/Time

Access

Read/write

Remarks

If a value is set to the CompletedDate property, Schedule+ places a check mark next to the task and draws a line through it to denote that the task has been completed. Also, the PercentCompleted property is set to 100.