SYMPTOMS
When you use the WEEKDAY function to compute the day of the week for dates prior to March 1, 1900 in Microsoft Excel 2000, the function returns an incorrect result.
For example, if you use the WEEKDAY function to determine the day of the week for February 16, 1900, Microsoft Excel returns 5, which indicates
that February 16 was a Thursday. The function should return 6, because February 16, 1900, was actually a Friday.
When you use the WEEKDAY function to find the day of the week for dates on or after March 1, 1900, the function returns the correct answer.
CAUSE
This problem occurs when the following conditions are true:
- You use the WEEKDAY function to determine the day of the week for dates prior to March 1, 1900.
-and-
- You use the 1900 date system.
WORKAROUND
To work around this problem, add one to the result of the formula as in
the following example:
=WEEKDAY("2/16/1900",1)+1
MORE INFORMATION
When the date system in Microsoft Excel was originally created, it was
designed to be fully compatible with date systems used by other
spreadsheet programs.
However, in this date system, the year 1900 is incorrectly interpreted as
a leap year. Because there is no February 29 ("leap day") in the year 1900,
the day of the week for any date before March 1, 1900 (the day after the
"leap day"), is not computed correctly.
Note that this only affects dates before March 1, 1900, and that the
error only occurs when you use the 1900 Date System in Microsoft Excel.
This problem does not occur if you are using the 1904 date system. When
you use the 1904 date system and the WEEKDAY function to compute the day of the week for dates prior to January 1, 1904, the function returns a #VALUE! error.
Additional query words:
year2000 y2k week day XL2000
Keywords : xlformula
Version : WINDOWS:2000
Platform : WINDOWS
Issue type : kbprb