System Agent Runs Tasks at Wrong Time/Day During Leap Year

ID: Q134357


The information in this article applies to:
  • Microsoft Windows 95
  • Microsoft Plus! for Windows 95


SYMPTOMS

In leap years, System Agent may run monthly tasks that should run on the 30th day of the month at the wrong time of day on the 28th of February. You expect System Agent to run the tasks at the correct time of day on February 29th.


CAUSE

The System Agent specification indicates that any day after the last day of the month is treated as the last day of the month. If a task is scheduled to begin at 11:59 P.M. on the 28th of February, and end at 12:00 A.M. on the 29th, the end time precedes the start time and the period is not what you expect.


STATUS

Microsoft is researching this problem and will post new information here in the Microsoft Knowledge Base as it becomes available.

Keywords :
Version :
Platform :
Issue type :


Last Reviewed: July 21, 1999
© 2000 Microsoft Corporation. All rights reserved. Terms of Use.