Managing the Migration Process

Previous Topic Next Topic

Team Roles During the Deploying Phase

During this phase, a subtle shift occurs in the dynamics of the project team. Here, the Logistics Manager will step to center stage. The Logistics Manager will often share the focus of the project with User Education as the systems are actively deployed, as users receive the appropriate training, and as the operations and support systems are activated. Table 2.11 shows the responsibilities of the project team during this phase:

Table 2.11   Team Roles During the Deploying Phase

Role Responsibility
Product Management Promotion, feedback, assessment, sign-off
Program Management Solution/scope comparison, stabilization management
Development Problem resolution, escalation support
Test Performance testing, problem identification
User Education Training, training schedule management
Logistics Site deployment management, change approval