Managing the Migration Process |
During this phase, a subtle shift occurs in the dynamics of the project team. Here, the Logistics Manager will step to center stage. The Logistics Manager will often share the focus of the project with User Education as the systems are actively deployed, as users receive the appropriate training, and as the operations and support systems are activated. Table 2.11 shows the responsibilities of the project team during this phase:
Table 2.11 Team Roles During the Deploying Phase
Role | Responsibility |
Product Management | Promotion, feedback, assessment, sign-off |
Program Management | Solution/scope comparison, stabilization management |
Development | Problem resolution, escalation support |
Test | Performance testing, problem identification |
User Education | Training, training schedule management |
Logistics | Site deployment management, change approval |